When i change the date of a task, i want the next tasks to change thier start date. That is the auto scheduling addon ( i think).
But when i do that, i don’t want to change the time between tasks.
Example :
task #1 : start today for a duration of 2 days
task #2 : start 3 days after the task #1.
if i move task #1 to start tomorrow, i want the task #2 is changed to start 3days after the task #1
Is it actually possible ?
If not, is it possible to add this for a future version of gantt ?
Hello,
If the tasks are linked, and links have the lag parameter, Gantt will keep the duration between tasks if the tasks have the ASAP constraint or don’t have constraints(compatibility mode).
In the following snippet, you can double-click on a link to set the lag parameter. After you drag the predecessor task, the successor task will keep the distance depending on the lag parameter: http://snippet.dhtmlx.com/5/403489417