I have a simple Task1 and Task2 and Task2 has 4 child asap constraint type tasks and each task starts consecutive days with 1 day duration. So structure is like below:
Task#1: start date: 2nd april and end date: 6th april
Task#2: start date: 2nd april
Task#2.1: start date 3rd april. duration 1
Task#2.2: start date 4th april. duration 1
Task#2.3: start date 5th april. duration 1
Task#2.4: start date 6th april. duration 1
So when i add a dependency from Task#1 to Task#2, all child tasks of Task#2 start date Expected to be 7th April as those are “asap” constraint type tasks. But those child tasks start dates are like 7th, 8th,9th and 10th.
Is this a issue or is there any thing i missed here?
Sample: https://snippet.dhtmlx.com/5/620dde6a0
Adde a link from Task#1 to Task#2 and see the child task dates.