Can it recognize the task relations of SS,SF,FF from the Project software


#1

Hi Dear Developer,

Can it recognize the task relations of SS,SF,FF when import .mpp file from the Project software?
Thanks.

Alex Chen


#2

Hello Alex,
Yes, when you import an MSP file, the link type should be correct. You can see how it works in the following sample:
https://docs.dhtmlx.com/gantt/samples/08_api/18_load_from_mpp.html
If there is an issue, please, reproduce it in the snippet, then click on the “Share” button and send me the link:
https://snippet.dhtmlx.com/38ee1b370
Or send me a ready demo with all the necessary Javascript and CSS files so that I can reproduce the issue locally.