I’ve got a problem where a start_to_finish dependency is incorrectly being calculated when I resize a task and I can’t quite figure out what’s going on. I’ve put together an example that isn’t working:
http://snippet.dhtmlx.com/5/c7f889df5
The example has a very basic structure
- Task 1
- Task 2
---- Task 2.1
There is one link between Task 2.1
and Task 1
. The link has a lag of 1 day.
- If I move
Task 2.1
forwards or backwards,Task 1
correctly moves forwards or backwards accordingly - If I resize
Task 2.1
start date,Task 1
does not get moved at all (incorrect given the dependency type)
- If I resize
Task 2.1
end date,Task 1
does move even though it shouldn’t
It seems like there’s something going wrong when resizing tasks. I’ve tried changing the constraint type and various other configuration options but I’ve not had any luck