Display two or more task in the same horizontal timeline

Hi all,

I have scenario where I need to display the task side by side (In the same horizontal line).

From looking at the photo, the left panel are the list of machines for our factory production, the right panel is the timeline of the machine usage from the production order.

The Gantt show the machine “Fleshing BH 001” is set for "Production Order no:1 at 06:00-06:30 and right side is set for “Production Order No: 2” at 07:00-08:00 (It’s in the same day but different time).

Can DHMLX Gantt handle such kind of scenario? and if yes how.

Thank you!!!

Hello Mal,
To show several tasks on the same row, you need to use the Split Tasks feature:
https://docs.dhtmlx.com/gantt/desktop__split_tasks.html
Here are examples of how it works:
https://docs.dhtmlx.com/gantt/samples/04_customization/11_split_task.html
https://docs.dhtmlx.com/gantt/samples/04_customization/21_open_split_task.html

Hello Ramil,
Thanks for the info and tips.

Cheers,