Like Microsoft project, does each task in GANTT have a fixed duration, fixed hours, and fixed resources?


#3

%E5%BE%AE%E4%BF%A1%E5%9B%BE%E7%89%87_20191231155005


#4

Hello Yansen,
Tasks always have fixed duration as assigning the resources doesn’t affect the duration. But it works that way because tasks and resources are separated. You need to implement a custom solution to change the task duration depending on the resources.

So, Gantt doesn’t have the features you listed, although it may work in a similar way.