Drag and drop in timeline view: contextual bug

Hi,

Just to make the issue clearer than my comment in this topic because it’s an old topic… : viewtopic.php?f=6&t=38175

With scheduler version 4.3.1 pro I have an issue with timeline view and cropped display hours (skipped hours, see linked topic for sample).

When dragging the event towards timeline end, as soon as the end of event reaches the timeline end, the event “grows” (incorrect event calculation, I guess it grows by skipped duration or so). This is a very annoying visual bug. The dropped time corresponds then to event display start time at drop, that’s consistent.

The bug does’nt appear when dropping event towards timeline start (also with cropped display hours) when setting up the option as stated in linked post.

Please can you consider this issue or maybe a workaround I could apply.

Thanks a lot,

EDIT : support ticket opened on June 1st.

Babs

I,ve the same problem. My timeline has 7 days. Each day consist of 8 hours(00 - 07).
When draging to the last our this Will happen
Time 07;45 then 00:00
Should be 07:45 then 08:00