Hi,

we have also durations with very small durations if the duration is too small no anchor is recognized for moving this little task. We don’t want to change the duration, only moving it in all x-modes like day, week, month. What can we do to solve this?

regards
Falk

I’m not quite sure what is the problem, if it occurs with latest beta - can you provide some sample ? ( by the way you can configure size of scale, it is not limited to days of fixed width )

I got the same problem.


The task is tiny you can get it and increase the duration.

Hello,

You can add new css class for tasks with low duration (by template) and increase their width to have the opportunity also drag them and not just increase duration.
Please check the snippet: docs.dhtmlx.com/gantt/snippet/5427e81a