How to handle task level calendars in auto-scheduling


#1

Hi DHTMLX Team,

We have an enterprise license of DHTMLX Gantt (6.3.0 version).
I am facing issue with auto-scheduling when i am using task level calendars with different working days and holidays along with link lag property to set lag and lead time between tasks. I am using forward planning with type 3 links between dependencies.
Then the start date of some tasks in not following the lag time passed in the links.
Note: I am not using time constraints still the task start and end dates are not correct after auto-scheduling.

But if I remove the task level calendars then the auto scheduling is working fine with lead and lag time between tasks.

Can you please check the same and revert back.


#2

Hello Divisree,
According to your description, it is similar to a known bug, but maybe there is something else.
To be sure, please reproduce the issue in the following snippet, then click on the “Share” button and send me the link:
http://snippet.dhtmlx.com/5/3fae1b026
Or send me a ready demo with all the necessary files so that I can reproduce the issue locally.