Hi DHTMLX Team,
We have an enterprise license of DHTMLX Gantt (6.3.0 version).
I am facing issue with auto-scheduling when i am using task level calendars with different working days and holidays along with link lag property to set lag and lead time between tasks. I am using forward planning with type 3 links between dependencies.
Then the start date of some tasks in not following the lag time passed in the links.
Note: I am not using time constraints still the task start and end dates are not correct after auto-scheduling.
But if I remove the task level calendars then the auto scheduling is working fine with lead and lag time between tasks.
Can you please check the same and revert back.