Example:
Task 13.12.2021 - 13.12.2021 Gannt considers as 0 days
And it’s logical because time is 13.12.2021 00:00:00 - 13.12.2021 00:00:00
But we have to make Gantt consider it as 1 day.
So we are doing normalization with callbacks and making end_date the end of day
13.12.2021 00:00:00 - 13.12.2021 23:59:59
And it worked okay until we started using auto-schedule.
When we have link
Task 1: 13.12.2021 00:00:00 - 13.12.2021 23:59:59 -> Task 2: 14.12.2021 00:00:00 - 14.12.2021 23:59:59
Auto-scheduling thinks that it’s not optimal and makes
Task 2: 13.12.2021 23:59:59 - 14.12.2021 23:59:58
And that’s not what we need.