Import file mpp. WBS are displaced in Gantt


#1

Hello
I uploaded a .mpp file to Gantt, however some of tasks in .mpp file were moved in Gantt
see detail in attached picture.

If you have any suggestion, please let me know
thank.


#2

Hello,
There is a bug when you import a file from MS Project with several root-levels in hierarchy tree, then some tasks are loaded under different parents. We are aware of this issue. The dev team will fix it in the future, but I cannot give you any ETA.
As a workaround, you can save the file in XML format, then resave the file in MPP format. After that, you can import the re-exported file in Gantt.
Please send us your MS Project file, where the issue is reproduced, so that we can test the issue locally.


#4

Hi,
MPP file attached,
please let we know when it is fixed.
thank

Master Schedule.mpp (454 KB)


#5

Hello,
Thanks for the attached file. I’ve sent it to our dev team, and they will test it.
I will inform you when the bug will be resolved.