From my understanding, the newest version of the Gantt was allowing this, but I can’t seem to find any proper documentation for it.
Did I misread? When I search, I mostly find information regarding moving multiple task in the timeline, but that’s not what I want. I want to be able to select multiple tasks and move them somewhere by dragging and dropping them.
Right now, there is no built-in feature to vertically reorder several tasks in the grid. The dev team will add that feature in the future, but I cannot give you any ETA.
For now, you need to implement a custom solution by using the Gantt API and Javascript.
Here is an example of how it can be implemented: https://snippet.dhtmlx.com/e1a9bf5x