Place the gant chart in the place where the mouse is removed

Hello, let me ask you a simple question!

Is there an option to place it on the spot where you removed the mouse after dragging it on the gant chart?
The width keeps adjusting automatically.

Please reply.
Thank you.

Hello,
By default, after you move or resize a task, Gantt rounds the dates to the nearest scale border. To change how it works, you need to disable the round_dnd_dates parameter:
https://docs.dhtmlx.com/gantt/api__gantt_round_dnd_dates_config.html
Here is an example:
http://snippet.dhtmlx.com/6f828f88b