example:
If I put an interval of 2 months, for example task starts and ends on 28/10/2016 04/11/2016 system is lost and shows the final date as 01.16.2017
The system is totally lost !!
Where is the resolution of this bug ?!

Hello,

Please, check the sample below. Start and end dates displayed correctly.
docs.dhtmlx.com/gantt/snippet/cd9128f3