timeline view x_unit: “day”,x_date: “%d %M”,I have meeting section, this section having more then one events its displayed one by one in particular date i need display each events as a separate rows like (add section) inside the meeting section .

It is not possible for scheduler in timeline view. You can use gantt, for which the above scenario is a default mode.

in gantt there is no timeline view we need 24 hours timeline with in a single cell in a secetion please help if you know that thanks in advance

The scale of gantt can be configured to show 24 hours, also its have the vertical list of sections/tasks, similar to the timeline view. Can you please specify which functionality of timeline view you are missing in case of the gantt ?