scheduler.markTimespan problem

In dhtmlxScheduler v.4.3.1 I am making good use of scheduler.markTimespan() to mark certain days in the Units view with multiple days.

In some very rare instances, the marked time spans for day 1 will appear on day 1 and also day 2 (when showing 2 days).

It would be pretty difficult to reproduce the problem and send you a working demo.

By some chance, is there a bug fix available I might be able to try?

I took the afternoon and created something which reproduces the problem.

What’s happening is I mark the timespan for a few hours on Friday March 11th and the timespan is also getting marked on Sat. March 12th for some reason.

I will send an email with a link to the demo. This took a lot to pull out of the application in order to show. I hope you’ll see something as our users are getting upset.

Brian

I have the same problem. please let me know when it’s fixed. thanks

Hi,
please contact support@dhtmlx.com or create a ticket in our support system.
It’s possible that similar bug has been fixed recently