Set a task resource exception

I assigned a task to three people, each of whom has their own calendar, and now there is no API to apply the calendar of three people to this task

Hello,
Unfortunately, there is no way to merge task calendars in the current Gantt version. The dev team will include that feature in the new version:

samples/02_extensions/18_linked_tasks.html Add lag to the relationship in Links but the page that appears after setting is not drawn according to the data

{
“id”: “25”,
“source”: “12”,
“target”: “19”,
“type”: “0”,
lag: “2”
}, {
“id”: “17”,
“source”: “18”,
“target”: “19”,
lag: “2”,
“type”: “0”
}

Hello Dangxiaowei,
Please, don’t ask the same questions in different topics.
Let’s continue our discussion there: