By setting gantt.config.work_time as true or false is working for whole project, May i know how can i set working days duration for specific task only ?
Likewise I have Task T1 and T2 In Project P1. Now I want to set T1 duration as weekend days true… How to make it ?
Hi,
Unfortunately it is possible to set the working time only for all tasks.