task duration hours..

Can i start the hour from 9 and end at 6 like office hours? not starting from 0 and end at 23…
one more is that can i omit weekends in my task duration?

It is not possible in current version, but we’ll add this feature in the nearest update, approx in late December - mid January

thz…

looking forward for the next version…

I’m curious - was the option to omit or factor in weekend days in task duration ever added to the product?

  • Ron

Hi,
yes, this functionality was added in version 2.1
It is possible to calculate duration of task using predefined working hours/days. In the current version it is a global setting, you can’t specify working time settings for individual tasks.
Set working time:
docs.dhtmlx.com/gantt/desktop__working_time.html
Do not display not working time on a scale
docs.dhtmlx.com/gantt/desktop__custom_scale.html

example:
docs.dhtmlx.com/gantt/samples/09 … r_day.html

Note, that in version 3.0 (the current one), API that allows not displaying a times on a scale was moved to PRO version of the component. i.e. it’s available only in Commercial and Enterprise versions of the Gantt