Tasks with no end date on the chart

Hi,

We have some tasks which does not have any end dates specified.
Like to know how that can be loaded to the grid.
Can such milestones data be loaded along with the other tasks which does have start and end dates?

Thanks in Advance.

Hi,
please clarify, do you mean the task that has no dates assigned (i.e. ‘unscheduled’ tasks), or tasks with start dates, but no end dates and duration (milestones)
for unscheduled tasks please check this article
docs.dhtmlx.com/gantt/desktop__c … duledtasks

And for milestones, you’ll need to specify the ‘type’ property of such items
docs.dhtmlx.com/gantt/desktop__milestones.html

Hi Aliaksandr,

We have the tasks with start date but no end date and duration, i.e milestones.
Is it that specifying milestones available only in PRO edition?

Thanks in Advance.

Hello,
yes, the different types of tasks (project, milestones) are available only in PRO version of the gantt. It can go under Commercial, Enterprise or Evaluation licenses